Hull 325 is at its final outfitting stage. It has left port with some ninety Trogir workers and is now docking at the Viktor Lenac Shipyard in Rijeka.
To finish the docking stage within the planned period, all the necessary preliminary works have been performed in the Trogir shipyard, different equipment has been thoroughly tested and systems for navigation to Rijeka and back to Trogir have been handed over, as well as those for test navigation after the return from the dock.
The tanker at the Rijeka dock will undergo corrosion protection of the hull and the removal of eye plates and the fore and aft cradle, as well as of other welded parts left from the launching. The tanker will be prepared for speed and fuel consumption measurement, and the built-in equipment will be tested and systems will be handed over to the classification society that supervises the shipbuilding.
After docking, the ship will leave port for test navigation, which should be performed within nine days. During navigation in the Split and Makarska waters, the tanker will undergo all measurements and a manoeuvrability test.
Upon returning to the homeport, all works will be finished and the remaining tests will be performed, before the ship is delivered.